Project #271
Improving Clearwell Design for CT Compliance
$213,200
Principal Investigator
Gil
Crozes
Research Manager
Albert L Ilges
Contractor
Carollo Engineers
Abstract
Evaluates (1) various design configurations to retrofit or design clearwells with baffle systems and/or (2) modification of flow configurations that maximize retention time to meet CT disinfection requirements. Research partner: USEPA. Published in 1999.